建设工程施工合同通用条款(99版中英文 上部分)
2013-12-18 07:20阅读:
General Conditions of Contract of
Construction
建设工程施工合同通用条款(99版)
GF-1999-0201
中华人民共和国建设部
国家工商管理局 制定
CONTENTS
Definitions and Interpretation of Contract Document
一、
词语定义及合同文件
1. Definitions
词语定义
2. Contract Document and
Order of Interpretation
合同文件及解释顺序
3. Official language and governing laws,
standards and codes
语言文字和适用法律、标准及规范
II Rights and
Obligations of the OWNER and CONTRACTOR二、
双方一般权利和义务
4. Engineer
工程师
5. The appointment and
instructions of an Engineer
工程师的委派和指令
6. Project manager
项目经理
7. The OWNER
responsibilities业主工作
8. The CONTRACTOR
responsibilities承包方工作
III Construction Program and
Time Limit for the Project三、
施工组织设计和工期
9 Progress
Schedule进度计划
10. Commencement and
postponement of the work 开工及延期开工
11 Suspension of the
construction work暂停施工
12. Delay of the time limit for
the work 工期延误
13 Completion of the
construction work
工程竣工
IV Quality and
Inspection四、质量与检验
14. Engineering quality
工程质量
15. Inspection and re-do the
work
检查和返工
16. Concealed work and
intermediate acceptance
隐蔽工程和中间验收
17 Re-inspection
重新检验
18. Engineering test run
工程试车
V Safety of Work
五、安全施工
19. Safety measures and safety
inspection 安全施工与检查
20 Safety
Protection安全防护
21 Safety
Accident 事故处理
VI Contract Sum &
Payment Methods
六、合同价款与支付
22 Contract Sum & Adjustments
合同价款及调整
23 Down payment for the
Works工程预付款
24 Confirmation of
engineering quantity工程量的确认
25 Progress Payment
(Progress Claim)
工程款(进度款)支付
VII Supply of material & equipment
七、
材料设备供应
26 Supply of material
& equipment by the OWNER 业主供应材料设备
27 Material and
equipment purchased by the
CONTRACTOR承包方采购材料设备
VIII Alteration of the Works
八、工程变更
28 Alteration of Design
工程设计变更
29 Other
alterations 其他变更
30 Confirmation of
alteration in price
确定变更价款
IX Completion and acceptance of
the work and final account
九、竣工验收与结算
31 Completion and
acceptance of the engineering work
竣工验收
32 Completion of
engineering work and final account
竣工结算
33 Engineering work
quality guarantee
质量保修
X Breach of the
contract, claim and dispute
十、
违约、索赔和争议
34 Breach of the
contract 违约
35 Claim
索赔
36 Dispute
争议
XI Others
十一、
其他
37 Subcontracting of the
engineering work
工程分包
38 Force de majeure
不可抗力
39 Insurance
保险
40 Guarantee
担保
41 Patent and special
technology
专利技术及特殊工艺
42 Cultural / historic
relic and underground obstacles
文物和地下障碍物
43 Termination of the
contract
合同解除
44 The contract goes
effective and termination of the contract
合同生效与终止
45 Number of the
contract copies
合同份数
46 Supplement Clauses
补充条款
Definitions and Interpretation of Contract Document
一、
词语定义及合同文件
1. Definitions
词语定义
Unless stated otherwise, the following words and expressions
shall have the meanings assigned to them as follows: -
下列词语除专用条款另有约定外,应具有本条所赋予的定义:
1.1 General Conditions of Contract: The
terms and conditions as stipulated in the General Conditions are in
accordance with applicable laws, administrative regulations and are
generally applicable to the construction & engineering
projects.
通用条款:
是根据法律、行政法规规定及建设工程施工的需要订立,通用于建设工程施工的条款。
1.2 Particular Conditions of
Contract: Agreed terms and conditions concluded between the OWNER
and the CONTRACTOR based on applicable laws and administrative
regulations, and mutual agreements reached particularly for this
Project.
专用条款:
是发包人与承包人根据法律、行政法规规定,结合具体工程实际,经协商达成一致意见的条款,是对通用条款的具体化、补充或修改。
1.3 OWNER: Person, firm, company or
other body named in this Contract as OWNER includes the OWNER's
personal representatives, successors and permitted assigns. The
OWNER possesses the Legal Person Status to enter into Contract and
pay the CONTRACTOR.
业主:
指在协议书中约定,具有工程发包主体资格和支付工程价款能力的当事人以及取得该当事人资格的合法继承人。
1.4
CONTRACTOR: Person, firm, company or other body named in this
Contract as CONTRACTOR to whom the Contract has been awarded by the
OWNER includes the CONTRACTOR's personal representatives,
successors and permitted assigns. The CONTRACTOR possesses the
Legal Person Status to enter into Contract and carry out the
Works.
承包方:
指在协议书中约定,被业主接受的具有工程施工承包主体资格的当事人以及取得该当事人资格的合法继承人。
1.5 Project Manager:
The person who has been appointed by the CONTRACTOR to be
responsible for the supervision of the project and contract
administration of the Contract named in the Particular Conditions
of Contract.
项目经理:指承包方在专用条款中指定的负责施工管理和合同履行的代表。
l. 6 Design
Institute: The design institute, holding valid Qualification
License, that has been entrusted by the OWNER to provide design
services for this project.
设计单位:指业主委托的负责本工程设计并取得相应工程设计资质等级证书的单位。
1.7 Supervision
Company: The supervision company, holding valid Qualification
License, that has been entrusted by the OWNER to provide
supervision services for this project.
监理单位:指业主委托的负责本工程监理并取得相应工程监理资质等级证书的单位。
1.8
Engineer: The chief supervision engineer appointed by the
supervision company to supervise the whole construction work or the
representative appointed by the OWNER for the administration of
this contract. The Engineer's Limit of Authority shall be defined
in the Particular Conditions of Contract.
工程师:
指本工程监理单位委派的总监理工程师或业主指定的履行本合同的代表,其具体身份和职权由业主承包方在专用条款中约定。
1.9
Construction Prices Administration Department: Administration
Department of the State Council, construction management department
of people government at county level and over, or any other
construction price administrative department entrusted by the
people government at various levels.
工程造价管理部门:
指国务院有关部门、县级以上人民政府建设行政主管部门或其委托的工程造价管理机构。
1.10 Works:
The Scope of Works as stipulated in this contract entered into
between the OWNER and the CONTRACTOR.
工程:指业主承包方在协议书中约定的承包范围内的工程。
1:11 Contract Sum:
The sum that has been agreed upon by the OWNER and the CONTRACTOR
in this Contract. The sum to be paid by the OWNER to the CONTRACTOR
who has completed the Works as per contract terms and conditions
and is responsible to make good any defects within the defects
liability period.
合同价款:指业主承包方在协议书中约定,业主用以支付承包方按照合同约定完成承包范围内全部工程并承担质量保修责任的款项。
1.12 Additional Contract Sum: In the course of the
implementation of the contract, additional contract sum is
incurred, which shall be calculated and added to the original
contract sum in accordance with the terms and conditions of the
Contract.
追加合同价款:指在合同履行中发生需要增加合同价款的情况,经业主确认后按计算合同价款的方法增加的合同价款。
1.13 Expense: Any expenses, whether the
expenses should be born by the OWNER and the CONTRACTOR, that are
not included in the Contract Sum;
费用:指不包含在合同价款之内的应当由业主或承包方承担的经济支出。
1.14 Contract Period: The total calendar
days (including public holidays) agreed by the OWNER and the
CONTRACTOR in the contract to be needed for the whole construction
work.
工期:指业主承包方在协议书中约定,按总日历天数(包括法定节假日)计算的承包天数。
1.15 Date of Commencement of
Work: The date agreed by the OWNER and the CONTRACTOR in the
contract to commence the Contract Works.
开工日期:指业主承包方在协议书中约定,承包方开始施工的绝对或相对的日期。
1.16 Date for Completion: The date
agreed by the OWNER and the CONTRACTOR in the contract to complete
the Contract Works.
竣工日期:指业主承包方在协议书约定,承包方完成承包范围内工程的绝对或相对的日期。
1.17 Drawings: The drawings
(including related notes and material) provided by the OWNER or by
the CONTRACTOR with approval by the OWNER, required for the
contraction of the contract works.
图纸:指由业主提供或由承包方提供并经业主批准,满足承包方施工需要的所有图纸(包括配套说明和有关资料)。
1.18 Construction Site: The place
provided by the OWNER to be used for the construction of the
project, which is clearly stipulated in the drawings.
施工场地:指由业主提供的用于工程施工的场所以及业主在图纸中具体指定的供施工使用的任何其他场所。
1.19 Written Documents: Means Contract
Documents, letters and digital telecommunications and digital
telecommunication (such as cable, telex, fax, electronic digital
exchange and E-mail, etc.) capable of reducing oral agreement into
written form.
书面形式:指合同书、信件和数据电文(包括电报、电传、传真、电子数据交换和电子邮件)等可以有形地表现所载内容的形式。
1.20 Liability for Breach of Contract:
The liability that the either party shall be responsible for not
honoring their respective contractual obligations or not fully
discharge their contractual obligations.
违约责任:指合同一方不履行合同义务或履行合同义务不符合约定所应承担的责任。
1.21 Claim: In the course of
implementation of the contract, any loss and/or expenses incurred
by the innocent party shall be compensated by the default party and
the Contract Period shall be extended accordingly.
索赔:指在合同履行过程中,对于并非自己的过错,而是应由对方承担责任的情况造成的实际损失,向对方提出经济补偿和(或)工期顺延的要求。
1.22 Force de majeure: Any occurrences
that cannot be foreseen, or avoided or overcome.
不可抗力:指不能预见、不能避免并不能克服的客观情况。
1.23 Hour or Date:
If hour is regarded as a unit in this
contract, which shall be calculated from the effective time
(excluding time for rest); If a date is used as a calculation unit,
the starting date shall not be calculated, but calculating from the
second date. If the time limit last date is a rest day or a public
holiday, then the next date to the rest day or a public day shall
be regarded as the final date except for the completion date. The
time limit of final day shall be 24:00 hour of the final
day.
小时或天:本合同中规定按小时计算时间的,从事件有效开始时计算(不扣除休息时间);规定按天计算时间的,开始当天不计入,从次日开始计算。时限的最后一天是休息日或者其他法定节假日的,以节假日次日为时限的最后一天,但竣工日期除外。时限的最后一天的截止时间为当日24时。
2. Contract Document and
Order of Interpretation
合同文件及解释顺序
2.l The documents in the
contract shall be mutually explanatory to each other. Apart from
those stipulated in the Particular Conditions of Contract, the
interpretation of the document in this contract shall be according
to the following order: -
合同文件应能相互解释,
互为说明。除专用条款另有约定外,组成本合同的文件及优先解释顺序如下:
l. Articles of
Agreement
本合同协议书
2. Particular Conditions
of Contract
本合同专用条款
3 General
Conditions of Contract
本合同通用条款
4 Standards,
Codes of Practice and relevant technical data / sheets
标准、规范及有关技术文件
5 Contract
Drawings 图纸
6 Bills of
Quantities 工程报价单或预算书
In the course of implementation of the contract, any
negotiations or changes reducing into document or written record of
negotiation and variation between the OWNER and the CONTRACTOR
shall be deemed to be the integral part of the
contract.
合同履行中,业主承包方有关工程的洽商、变更等书面协议或文件视为本合同的组成部分。
2.2 When there is any inconsistency or discrepancy appeared
in the Contract Document, both the OWNER and the CONTRACTOR shall
endeavor to reach settlement on the conditions that the progress of
Works are not affected. Both parties can also request the
supervision engineer to interpret the inconsistency or discrepancy
arisen. In the event that both parties cannot
reach mutual agreement or disagree with the interpretation of the
supervision engineer then the disputes shall be dealt with as per
Clause 37 of the General Conditions of Contract.
当合同文件内容含糊不清或不相一致时,
在不影响工程正常进行的情况下,由业主承包方协商解决。双方也可以提请负责监理的工程师作出解释。双方协商不成或不同意负责监理的工程师作出解释。双方协商不成或不同意负责监理的工程师的解释时,按本通用条款第37条关于争议的约定处理。
3. Official language and governing laws,
standards and codes
语言文字和适用法律、标准及规范
3.1 Language语言文字
This contract is in English and is interpreted in Chinese
language. If two or more languages are stipulated in the Particular
Conditions of Contract for the contract document and, then Chinese
language shall be regarded as a standard language for
interpretation of the Contract Document.
本合同文件使用汉语语言文字书写、解释和说明。如专用条款约定使用两种以上(含两种)语言文字时,汉语应为解释和说明本合同的标准语言文字。
In the minority nationalities area, the two parties can reach
an agreement that the contract to be made and interpreted in the
language of a minority nationality.
在少数民族地区,双方可以约定使用少数民族语言文字书写和解释、说明本合同。
3.2 Governing laws and
regulations适用法律和法规
This contract is in conformity with current state laws and
administrative regulations. Particular provisions of laws and
regulations shall be clearly stipulated and defined in the
Particular Conditions of Contract.
本合同文件适用国家的法律和行政法规。需要明示的法律、行政法规,由双方在专用条款中约定。
3.3
Standards and Codes适用标准、规范
The standards and codes to be adopted shall be agreed by the
two parties in the Particular Conditions of Contract; if no such
standards or codes are stipulated in the contract, the two parties
shall agree of the standards and codes of the respective
industries. The OWNER shall provide the CONTRACTOR a list of the
standards and codes to be adopted in the works in two copies within
the deadline as stipulated in the Particular Conditions of
Contract.
双方在专用条款内约定适用国家标准、规范的名称;没有国家标准、规范但有行业标准、规范的,约定适用行业标准、规范的名称;没有国家和行业标准、规范的,约定适用工程所在地地方标准、规范的名称。业主应按专用条款约定的时间向承包方提供一式两份约定的标准、规范。
If there is no such corresponding standards or codes in the
country, the OWNER shall provide the CONTRACTOR with the technical
requirements within the deadline as stipulated in the Particular
Conditions of Contract. The CONTRACTOR shall submit the technical
standards to the OWNER for approval and execute the Works in
accordance with the approved technical standards after approval by
the OWNER. If the OWNER requires that foreign standards or codes to
be adopted, then the OWNER is responsible to provide the CONTRACTOR
with the Chinese version of the relevant standards or
codes
国内没有相应标准、规范的,由业主按专用条款约定的时间向承包方提出施工技术要求,承包方按约定的时间和要求提出施工工艺,经业主认可后执行。业主要求使用国外标准、规范的,应负责提供中文译本。
The OWNER shall be responsible for any expenses incurred in
purchase and translation of these standards and codes or the
technical standards.
本条所发生的购买、翻译标准、规范或制定施工工艺的费用,由业主承担。
II Rights and
Obligations of the OWNER and CONTRACTOR二、
双方一般权利和义务
4. Engineer
工程师
4.l If the project
engineering to be carried out under supervision system, the OWNER
shall inform the CONTRACTOR in written form the name of supervision
company, scopes of supervision work and the supervision limits of
authority.
实行工程监理的,
业主应在实施监理前将委托的监理单位名称、监理内容及监理权限以书面形式通知承包方。
4.2 The chief supervisor
entrusted by the supervision company for this project is entitled
as Engineer in this contract. His name, post,
functions and power shall be indicated by the OWNER in the
Particular Conditions of Contract. The Engineer shall execute his
functions and power as required in the Particular Conditions of
Contract. The OWNER requires that the Engineer shall have approval
from the OWNER when implementing some of his functions and power.
The appointment of the Engineer shall have approval by the
OWNER.
监理单位委派的总监理工程师在本合同中称工程师,其姓名、职务、职权由业主承包方在专用条款内写明。工程师按合同约定行使职权,业主在专用条款内要求工程师在行使某些职权前需要征得业主批准的,工程师应征得业主批准。
4.3 The person sent to the
construction site by the OWNER as its representative for the
implementation of the contract is also called as Engineer. His
name, post, functions and power shall be indicated in the
Particular Conditions of Contract by the OWNER. His functions and
power shall not be overlapped with those of the Engineer appointed
by the supervision company. Whenever overlapping functions and
power found or they are not clear, the OWNER shall be responsible
for the clarification and inform the CONTRACTOR in written
form.
业主派驻施工场地履行合同的代表在本合同中也称工程师,其姓名、职务、职权由业主在专用条款内写明,但职权不得与监理单位委派的总监理工程师职权相互交叉。双方职权发生交叉或不明确时,由业主予以明确,并以书面形式通知承包方。
4.4 In the implementation of the
contract, any conflict between the OWNER and CONTRACTOR in the
field of rights and obligations, the supervision Engineer shall
deal with the case in just and fair manner and within his functions
and power. If either party has objection to the settlement result
by the supervision Engineer, it can be settled as per Clause 37 on
dispute.
合同履行中,
发生影响业主承包方双方权利或义务的事件时,负责监理的工程师应依据合同在其职权范围内客观公正地进行处理。一方对工程师的处理有异议时,按本通用条款第37条关于争议的约定处理。
4.5 Apart from those clearly
stipulated in the contract or approval by the OWNER, the
supervision Engineer has no right to rescind any rights and
obligations of the OWNER that has been agreed in the
contract.
除合同内有明确约定或经业主同意外,
负责监理的工程师无权解除本合同约定的承包方的任何权利与义务。
4.6 If no supervision system is
applied over the construction work, the term Engineer means the
representative appointed by the OWNER to the construction site for
the implementation of the contract, whose specific functions and
power shall be indicated by the OWNER in the Particular Conditions
of Contract.
不实行工程监理的,
本合同中工程师专指业主派驻施工场地履行合同的代表,其具体职权由业主在专用条款内写明。
5. The appointment and
instructions of an Engineer
工程师的委派和指令
5.1 The Engineer Representative
can entrust an engineer representative to execute his functions and
power indicated in the contract and can remove such entrustment
when necessary. The OWNER shall inform the CONTRACTOR such
entrustment or removal 7 days in advance. The supervision Engineer
shall inform the OWNER the entrustment or removal of a
representative. The letter of entrustment and removal shall be kept
as an integrated part of the contract.
工程师可委派工程师代表, 行使合同约定的自己的职权,
并可在认为必要时撤回委派。委派和撤回均应提前7天以书面形式通知承包方,负责监理的工程师还应将委派和撤回通知业主。委派书和撤回通知作为本合同附件。
Any written form letter or material to the OWNER by the
representative of the Engineer have equal effect as those issued by
the Engineer himself When the CONTRACTOR has any doubt over the
written form letter and material, they can submit such letter or
material to the Engineer himself for confirmation. When these
instructions proved to be incorrect, the Engineer shall correct
them accordingly.
工程师代表在工程师授权范围内向承包方发出的任何书面形式的函件,与工程师发出的函件具有同等效力。承包方对工程师代表向其发出的任何书面形式的函件有疑问时,可将此函件提交工程师,工程师应进行确认。工程师代表发出指令有失误时,工程师应进行纠正。
None but the Engineer or his representative has right to
issue instructions for the contract.
除工程师或工程师代表外,业主派驻工地的其他人员均无权向承包方发出任何指令。
5.2 The Engineer instructions,
notice to be signed by himself and submit to the project manager.
The instructions become effective after the signature by the
project manager at the time of reception. When necessary the
Engineer can issue verbal instruction, which shall be confirmed
within 24 hours, the CONTRACTOR should carry out the verbal
instruction accordingly. If the Engineer is unable to confirm his
verbal instruction in time, then the CONTRACTOR shall request a
written confirmation from the Engineer within 7 days after the
verbal instruction released. The verbal instruction shall be deemed
to be confirmed if the Engineer does feedback his confirmation
within 48 hours after the receipt of the request.
工程师的指令、
通知由其本人签字后,以书面形式交给项目经理,项目经理在回执上签署姓名和收到时间后生效。确有必要时,工程师可发出口头指令,并在48小时内给予书面确认,承包方对工程师的指令应予执行。工程师不能及时给予书面确认的,承包方应于工程师发出口头指令后7天内提出书面确认要求。工程师在承包方提出确认要求后48小时内不予答复的,视为口头指令已被确认。
When the CONTRACTOR hold that the
instruction issued by the Engineer is irrational, they shall submit
a written report to the Engineer for the revision of the
instruction within 24 hours after the receipt of the instruction,
the Engineer shall clearly response to this report, either re-issue
in written the revised instruction or the decision to maintain
original instruction unchanged. Under some critical conditions, the
Engineer demands that the CONTRACTOR immediately carry out his
instruction while the CONTRACTOR put forward their doubt over it,
but the Engineer insists on his instruction to be implemented, in
such case the CONTRACTOR shall carry out the instruction. The OWNER
shall be responsible for any additional variation to the contract
sum resulting from the implementation of the wrong instruction and
the construction progress shall be duly postponed.
承包方认为工程师指令不合理,应在收到指令后24小时内向工程师提出修改指令的书面报告,工程师在收到承包方报告后24小时内作出修改指令或继续执行原指令的决定,并以书面形式通知承包方。紧急情况下,工程师要求承包方立即执行的指令或承包方虽有异议,但工程师决定仍继续执行的指令,承包方应予执行。因指令错误发生的追加合同价款和给承包方造成的损失由业主承担,延误的工期相应顺延。
The above term is also applicable to the instruction or
notice issued by the Engineer representative.
本款规定同样适用于由工程师代表发出的指令、通知。
5.3 The Engineer shall issue
timely instructions to the CONTRACTOR and approve other obligations
as stipulated in the contract. The OWNER shall be responsible for
any additional cost to the contract sum and the postponement of the
work progress and relevant loss incurred because of the Engineer
fails to implement his obligations as required in the
contract.
工程师应按合同约定,及时向承包方提供所需指令、批准并履行约定的其他义务。由于工程师未能按合同约定履行义务造成工期延误,业主应承担延误造成的追加合同价款,并赔偿承包方有关损失,顺延延误的工期。
5.4 If there is need to change
the place of the Engineer, the OWNER shall inform the CONTRACTOR
this decision at least 7 days in advance
如需更换工程师,业主应至少提前7天以书面形式通知承包方,后任继续行使合同文件约定的前任的职权,履行前任的义务。
6. Project manager
项目经理
6.1 Name and post of the project
manager shall be indicated in the Particular Conditions of
Contract
项目经理的姓名、职务在专用条款内写明。
6.2 Any instruction issued by
the CONTRACTOR as stipulated in the contract shall be in written
form and signed by the project manager and pass to the Engineer.
The instruction goes effective at the time when the Engineer signs
his name on the receipt.
承包方依据合同发出的通知,
以书面形式由项目经理签字后送交工程师,工程师在回执上签署姓名和收到时间后生效。
6.3 The
project manager organizes the construction work as per the
construction program approved by the OWNER and the instructions
issued by the Engineer as required in the contract. When impossible
to contact with the Engineer, the project manager shall first take
emergent measures to protect the life of the workers in the site
and ensure the property safety of the project and submit a report
about it to the Engineer within 48 hours of the measures taken. If
the OWNER or the third party is responsible for this, they shall be
responsible for the additional cost to the contract sum and
postponement of progress duly; if the CONTRACTOR is responsible for
it, the CONTRACTOR shall be responsible for any cost incurred and
the progress schedule shall not be postponed.
项目经理按业主认可的施工组织设计(施工方案)和工程师依据合同发出的指令组织施工。在情况紧急且无法与工程师联系时,项目经理应当采取保证人员生命和工程、财产安全的紧急措施,并在采取措施后48小时内向工程师关交报告。责任在业主或第三人,由业主承担由此发生的追加合同价款,相应顺延工期;责任在承包方,由承包方承担费用,不顺延工期。
6.4 If the CONTRACTOR wishes to
change the place of the Project manager, they shall inform the
OWNER at least 7 days in advance and obtain the approval from the
OWNER. The successor shall execute all the functions and power of
his predecessor and implement his obligations as required in the
contract.
承包方如需要更换项目经理,应至少提前7天以书面形式通知业主,关征得业主同意。后任继续行使合同文件约定的前任的职权,履行前任的义务。
6.5 The OWNER can put forward
their suggestion to change the project manager via negotiation with
the CONTRACTOR when they think that the project manager does not
deserve his post.
业主可以与承包方协商, 建议更换其认为不称职的项目经理。
7. The OWNER
responsibilities业主工作
7.1 The OWNER shall complete the
following work within the deadline as required in the Particular
Conditions of Contract.
业主按专用条款约定的内容和时间完成以下工作:
7.1.1
Complete the procedure of land requisition,
compensation for the original occupants and leveling of the site to
meet the construction requirement and continue to be responsible
for the settlement of any practical problems arising
therefrom.
办理土地征用、拆迁补偿、平整施工场地等工作,使施工场地具备施工条件,在开工后继续负责解决以上事项遗留问题;
7.1.2
Temporary power / water / telecommunication line
tie-in to the designated spots in the construction site from
outside as specified in the Particular Conditions of Contract so as
to ensure the construction requirement.
将施工所需水、电、电讯线路从施工场地外部接至专用条款约定地点,保证施工期间的需要;
7.1.3
Road access to the site from public traffic road
system and main road in the site area as specified in the
Particular Conditions of Contract so as to meet the requirement for
the construction work and ensure easy access to the
site.
开通施工场地与城乡公共道路的通道,以及专用条款约定的施工场地内的主要道路,满足施工运输的需要,保证施工期间的畅通;
7.1.4
Provide the CONTRACTOR any data of geological survey
and underground piping / cable system. The OWNER shall ensure that
the data they provide is true and authentic.
向承包方提供施工场地的工程地质和地下管线资料,对资料的真实准确性负责;
7.1.5
Completion of the procedures for any permit
certificates for the construction of the project and any relevant
approved document from the local authorities and obtain the
approval certificate necessary for the construction work such as
temporary land use permit, application for temporary cut off power
/ water supply, temporary blockade of traffic road and carry out
explosion work (excluding the qualification certificate for the
CONTRACTOR).
办理施工许可证及其他施工所需证件、批件和临时用地、停水、停电、中断道路交通、爆破作业等的申请批准手续(证明承包方自身资质的证件除外);
7.1.6
Confirmation of bench mark and coordinate control
point, and inform the CONTRACTOR the above data in written form and
jointly re-check at the site.
确定水准点与座标控制点,以书面形式交给承包方,进行现场交验;
7.1.7
Organize a joint drawings review with design
institute and the CONTRACTOR and put all the technical information
to be known on the table.
组织承包方和设计单位进行图纸会审和设计交底;
7.1.8
Coordinate and settle the problems between the
underground piping / cable system and the nearby construction
buildings (including the ancient buildings and structure to be
protected and preserved) and famous ancient trees, the OWNER is
responsible for any relevant cost incurred.
协调处理施工场地周围地下管线和邻近建筑物、构筑物(包括文物保护建筑)、古树名木的保护工作、承担有关费用;
7.1.9
Any other work and responsibilities to be stipulated
in the Particular Conditions of Contract by the two
parties.
业主应做的其他工作,双方在专用条款内约定。
7.2 The OWNER can entrust the
CONTRACTOR to complete the work and responsibilities in Clause 7.1,
which shall be indicated in the Particular Conditions of Contract
and the cost for the work shall be on the OWNER
account.
业主可以将7.1款部分工作委托承包方办理,双方在专用条款内约定,其费用由业主承担。
7.3 If the OWNER fails to
implement the work and responsibilities set in Clause 7.1 and
result in the delay of the construction progress, they shall be
responsible for any loss incurred to the CONTRACTOR and the
construction progress schedule shall be duly
postponed.
业主未能履行7.1款各项义务,导致工期延误或给承包方造成损失的,业主赔偿承包方有关损失,顺延延误的工期。
8. The CONTRACTOR
responsibilities承包方工作
8.1 The CONTRACTOR shall
complete the following work within the designated limit of time as
stipulated in the Special Provisions.
承包方按专用条款约定的内容和时间完成以下工作:
8.1.1
According to the entrustment of the OWNER, the
CONTRACTOR can complete construction drawings or some auxiliary
design within their qualification grade and business scope, the
OWNER will be responsible for the expense incurred when the above
work is confirmed the OWNER.
根据业主委托,在其设计资质等级和业务允许的范围内,完成施工图设计或与工程配套的设计,经工程师确认后使用,业主承担由此发生的费用;
8.1.2
Submit to the Engineer the annual / quarterly /
monthly progress schedule and relevant progress statistics
report.
向工程师提供年、季、月度工程进度计划及相应进度统计报表
8.1.3
Provide lighting and barricade facilities applied
during night overwork and security personnel for the
work.
根据工程需要,提供和维修非夜间施工使用的照明、围栏设施,产负责安全保卫
8.1.4
Provide the OWNER site office space and some living
facilities as stipulated in the Special Provisions, but the expense
incurred shall be on the OWNER account.
按专用条款约定的数量和要求,向业主提供施工场地办公和生活的房屋及设施,业主承担由此发生的费用
8.1.5
Adhere administrative regulations on construction
site traffic, noise control and environmental protection and safety
work issued by the local authorities and complete required
procedures, and inform the OWNER in written form of their work, the
OWNER shall be responsible for any expense incurred except the fine
and penalty sum resulting from the fault of the
CONTRACTOR.
遵守政府有关主管部门对施工场地交通、施工噪音以及环境保护和安全生产等的管理规定,按规定办理有关手续,并以书面形式通知业主,业主承担由此发生的费用,因承包方责任造成的罚款除外
8.1.6
As per the stipulations set in the Special
Provisions the CONTRACTOR is required to protect the finished item
of work that has not yet been formerly accepted. The CONTRACTOR
shall be responsible for any damage and repair work; if the OWNER
requires the CONTRACTOR to take special care on the protection of
some items of work, additional cost shall be added to the contract
sum, which shall be stipulated in the Special
Provisions.
已竣工工程未交付业主之前,承包方按专用条款约定负责已完工程的保护工作,保护期间发生损坏,承包方自费予以修复;业主要求承包方采取特殊措施保护的工程部位和相应的追加合同价款,双方在专用条款内约定
8.1.7
Take proper measures to protect underground piping /
cable system, buildings, structure and ancient trees around
(including ancient buildings) as stipulated in the Special
Provisions.
按专用条款约定做好施工场地地下管线和邻近建筑物、构筑物(包括文物保护建筑)、古树名木的保护工作;
8.1.8
Good house-keeping at construction site and adhere
regulations on environmental protection and hygiene, clean the
construction site at the time of handing-over to the requirement as
set in the Special Provisions and is responsible for any penalty
resulting from the fault of their own.
保证施工场地清洁符合环境卫生管理的有关规定,交工前清理现场达到专用条款约定的要求,承担因自身原因违反有关规定造成的损失和罚款;
8.1.9
Any other work as agreed by the both parties as
required in the Special Provisions
承包方应做的其他工作,双方在专用条款内约定。
8.2 The CONTRACTOR shall be
responsible for any loss to the OWNER resulting from the fault of
the CONTRACTOR when implementing the responsibilities in Clause
8.1
承包方未能履行8.1款各项义务,造成业主损失的,承包方赔偿业主有关损失
III Construction Program and
Time Limit for the Project三、
施工组织设计和工期
9 Progress
Schedule进度计划
9.1 The CONTRACTOR is required
to submit construction program for the work and progress schedule
to the Engineer within the deadline stipulated in the Special
Provisions. The Engineer shall confirm or put forward his comments
over the construction program and progress schedule within the
deadline as stipulated in the Special Provisions. If they are not
confirmed or the Engineer does not provide his comments over them,
it shall be deemed to be approved.
承包方应按专用条款约定的日期,将施工组织设计和工程进度计划提交修改意见,逾期不确认也不提出书面意见的,视为同意。
9.2 The single item of work in a
complex engineering work to be built by stages, the CONTRACTOR
shall compile the progress schedule for separate item of work as
per the drawings supplied by the OWNER and the relevant material,
the specific contents of which is agreed by the both parties in the
Particular Conditions.
群体工程中单位工程分期进行施工的,承包方应按照业主提供图纸及有关资料的时间,按单位工程编制进度计划,其具体内容双方在专用条款中约定。
9.3 The CONTRACTOR shall proceed
their work as per the progress schedule already confirmed by the
Engineer and shall accept the inspection and supervision from the
Engineer. When the actual construction progress is not in
conformity with the confirmed progress schedule, the CONTRACTOR is
required to submit the improvement measures as per the requirement
by the Engineer and precede the work after the confirmation from
the Engineer. The CONTRACTOR shall not raise any request for the
additional cost for the improvement measures taken because of
delayed construction progress totally out of their
fault.
承包方必须按工程师确认的进度计划组织施工,接受工程师对进度的检查、监督。工程实际进度与经确认的进度计划不符时,承包方应按工程师的要求提出改进措施,经工程师确认后执行。因承包方的原因导致实际进度与进度计划不符,承包方无权就改进措施提出追加合同价款。
10. Commencement and
postponement of the work 开工及延期开工
10.1 The CONTRACTOR shall start the construction work on the
date already stipulated in the agreement. When the CONTRACTOR find
unable to start the work as required, they shall submit an
application of the postponement of commencement of work and put
forward the reason 7 days prior to the scheduled date. The Engineer
shall make a reply to the CONTRACTOR for their application in
written form within 48 hours at the receipt of the application. If
the Engineer does not reply to this application within 48 hours it
shall be deemed that the Engineer has approved their application
and the construction progress shall be duly postponed. If the
Engineer does not agree the postponement of the construction
progress or the CONTRACTOR does not put forward their application
within stipulated time, the original construction progress shall
not be postponed.
承包方应当按照协议书约定的开工日期开工。承包方不能按时开工,应当不迟于协议书约定的开工日期前7天,以书面形式向工程师提出延期开工的理由和要求。工程师应当在延期开工申请后48小时内以书面形式答复承包方,工程师在延期开工申请后48小时内不答复,视为同意承包方要求,开工日期相应顺延。工程师不同意延期要求或承包方未在规定时间提出延期开工要求,开工日期不予顺延。
10.2 In case the construction work cannot start as per
scheduled date in the agreement out of the fault on the part of the
OWNER, the Engineer shall inform the CONTRACTOR in written form
that the commencement of work shall be postponed. The OWNER shall
be responsible for the loss incurred and the construction progress
shall be duly postponed.
因业主原因不能按照协议书约定的开工日期开工,工程师应以书面形式通知承包方,推迟开工日期。业主赔偿承包方因延期开工造成的损失,并相应顺延工期。
11 Suspension of the
construction work暂停施工
When the Engineer deems it necessary to suspend the
construction work, he shall inform the CONTRACTOR in written form
to suspend the work and put forward written comments to deal with
the issue within 48 hours. The CONTRACTOR shall suspend the work as
required and make proper care to protect the finished work. When
the CONTRACTOR has proceeded what the Engineer requested, they can
submit the written request to resume the work, the Engineer shall
make a reply to this request within 48 hours at the receipt of the
request. If the Engineer cannot provide the proposal over it or
fails to give a firm reply to it within 48 hours, the CONTRACTOR
can resume the construction work at their will. Any suspension of
work results from the fault of the OWNER, they shall be responsible
for the additional cost incurred and the construction progress be
postponed accordingly; the CONTRACTOR shall be responsible for any
cost incurred for the suspension of work due to the fault on their
part, and the construction progress shall not be
postponed.
工程师认为确有必要暂停施工时,应当以书面形式要求承包方暂停施工,并在提出要求后48小时内提出书面处理意见。承包方应当按工程师要求停止施工,并妥善保护已完工程。承包方实施工程师作出的处理意见后,可以书面形式提出复工要求,工程师作出的处理意见后,可以书面形式提出复工要求,工程师应当在48小时内给予答复。工程师未能在规定时间内提出处理意见,或收到承包方复工要求后48小时内未予答复,承包方可自行复工。因业主原因造成停工的,由业主承担所发生的追加合同价款,赔偿承包方由此造成的损失,相应顺延工期;因承包方原因造成停工的,由承包方承担发生的费用,工期不予顺延。
12. Delay of the time limit for
the work 工期延误
12.1 Time limit for the work shall be postponed for the one
of the following reasons with the confirmation by the
Engineer.
因以下原因造成工期延误,经工程师确认,工期相应顺延:
12.1.1 The OWNER
fails to provide the CONTRACTOR drawings and necessary conditions
for carrying out the construction work as stipulated in the
Particular Conditions of Contract;
业主未能按专用条款的约定提供图纸及开工条件;
12.1.2 The
CONTRACTOR fails to pay the CONTRACTOR down payment, progress claim
within the designated period thus affect the CONTRACTOR to carry
out their normal construction work.
业主未能按约定日期支付工程预付款、进度款,致使施工不能正常进行;
12.1.3 Normal
work is unable to be carried out due to the Engineer not issuing
instructions or approval to the CONTRACTOR as per terms stipulated
in the contract.
工程师未按合同约定提供所需指令、批准等,致使施工不能正常进行;
12.1.4 Design
change result in additional work
load.设计变更和工程量增加;
12.1.5 Power / water / gas
supply failure which affecting the works for more than accumulated
8 hours within one week not due to the fault of
the CONTRACTOR.
一周内非承包方原因停水、停电、停气造成停工累计超过8小时;
12.1.6 Force de
majeure.不可抗力;
12.1.7 Any other
reasons that have already been stipulated in the Particular
Conditions of Contract or approved by the Engineer;
专用条款中约定或工程师同意工期顺延的其他情况。
12.2 When case in Clause 12.1 occurs, the CONTRACTOR is
required to submit a report on the delay of the work progress to
the Engineer within 14 days. The Engineer shall reply and give
opinion within 14 days after the receipt of the report, if the
Engineer does not do so within the designated period, it shall be
deemed that the Engineer has agreed their report and the work
progress can be postponed.
承包方在12.1款情况发生后14天内,就延误的工期以书面形式向工程师提出报告。工程师在收到报告后14天内予以确认,逾期不予确认也不提出修改意见,视为同意顺延工期。
13 Completion of the
construction work
工程竣工
13.1 The CONTRACTOR shall complete the work by the date as
per the stipulation in the contract or per the postponed date
agreed by the Engineer
承包方必须按照协议书约定的竣工日期或工程师同意顺延的工期竣工。
13.2 The construction work cannot be completed by the date as
per the stipulation in the contract or per the postponed date
agreed by the Engineer for the CONTRACTOR reason, the CONTRACTOR
shall be responsible for the liability of breach of the
contract.
因承包方原因不能按照协议书约定的竣工日期或工程师同意顺延的工期竣工的,承包方承担违约责任。
13.3 If necessary, the OWNER requests the construction work
to be completed ahead of the schedule, an agreement concluded by
the two parties is required on this issue, which shall be an
integrated part of the whole contract. This agreement on earlier
completion of the contractual work shall include measures to be
taken by the CONTRACTOR to ensure the work quality and safety work
while the OWNER shall provide necessary conditions for earlier
completion of the work and the sum of additional cost for this
earlier completion of work.
施工中业主如需提前竣工,双方协商一致后应签订提前竣工协议,作为合同文件组成部分。提前竣工协议应包括承包方为保证工程质量和安全采取的措施、业主为提前竣工提供的条件以及提前竣工所需的追加合同价款等内容。
IV Quality and
Inspection四、质量与检验
14. Engineering quality
工程质量
14.1 The engineering quality shall meet the designated
requirement as stipulated in the agreement, engineering quality
verification is based on State Standards currently applicable. The
CONTRACTOR shall be responsible for any quality defects not up to
the required standards.
工程质量应当达到协议书约定的质量标准,质量标准的评定以国家或行业的质量检验评定标准为依据。因承包方原因工程质量达不到约定的质量标准,承包方承担违约责任。
14.2 In the event that there are any disputes arising from
the quality of works, both parties agree to submit the disputes to
the Quality Control Station for disputes settlement. Any costs
incurred shall be born by the defaulting parties. If both parties
are liable then the costs shall be shared according to the degree
of faults.
双方对工程质量有争议,由双方同意的工程质量检测机构鉴定,所需费用及因此造成的损失,由责任方承担。双方均有责任,由双方根据其责任分别承担。
15. Inspection and re-do the
work
检查和返工
15.l The CONTRACTOR is required to carry
out the construction work strictly as per standards, codes and
requirement in the drawings and instructions from the Engineer.
They should provide any convenient conditions for the OWNER to
inspect the work at any time.
承包方应认真按照标准、规范和设计图纸要求以及工程师依据合同发出的指令施工,随时接受工程师的检查检验,为检查检验提供便利条件。
15.2 Once the Engineer finds any of the engineering work is
not in conformity with the required standard, he shall instruct the
CONTRACTOR to tear down the unqualified item of work and re-do it
again and the CONTRACTOR shall follow the Engineer instructions to
tear down the sub-engineering work and re-do it again. The
CONTRACTOR shall be responsible for the cost incurred if they are
responsible for the poor work quality in the case and the work
progress shall not be postponed.
工程质量达不到约定标准的部分,工程师的要求拆除和重新施工,直到符合约定标准。因承包方原因达不到约定标准,由承包方承担拆除和重新施工的费用,工期不予顺延。
15.3 The Engineer shall not affect normal work of the
CONTRACTOR in the course of his inspection work. If the inspection
does affect the normal work of the CONTRACTOR, and the work later
to be unqualified, then the CONTRACTOR shall be responsible for the
cost resulting from the inspection work. In other cases the OWNER
shall be responsible for the cost incurred because of inspection
work and the work progress shall be postponed
accordingly.
16.3工程师的检查检验不应影响施工正常进行。如影响施工正常进行,检查检验不合格时,影响正常施工的费用由承包方承担。除此之外影响正常施工的追加合同价款由业主承担,相应顺延工期。
15.4 The OWNER shall bear additional cost in the contract
value incurred due to wrong instructions the Engineer issued or any
other reasons not by the CONTRACTOR.
因工程师指令失误或其他非承包方原因发生的追加合同价款,由业主承担。
16. Concealed work and
intermediate acceptance
隐蔽工程和中间验收
16.1 When the engineering is under concealed condition or is
ready for intermediate acceptance as per the terms set in
Particular Conditions of Contract, the CONTRACTOR shall first make
a self-inspection, and inform the Engineer in written form for
acceptance 24 hours prior to the concealment and intermediate
acceptance. The notice shall consist of the following contents such
as contents of the acceptance, place and date and time of the
acceptance. The CONTRACTOR shall prepare the acceptance records. If
the acceptance proves to be qualified, the engineer shall sign on
the acceptance record form and the CONTRACTOR may resume their
concealed work. If the work proves unqualified, the CONTRACTOR
shall repair or re-do the work within the period designated by the
Engineer for the following re-acceptance.
工程具备隐蔽条件或达到专用条款约定的中间验收部位,承包方进行自检,并在隐蔽或中间验收前48小时以书面形式通知工程师验收。通知包括隐蔽和中间验收的内容、验收时间和地点。承包方准备验收记录,验收合格,工程师在验收记录上签字后,承包方可进行隐蔽和继续施工。验收不合格,承包方在工程师限定的时间内修改后重新验收。
16.2 If the Engineer is unable to carry out the inspection
works, then the Engineer should inform the CONTRACTOR 24 hours in
advance. In any event the extension should not be more than 48
hours. If the Engineer can not give notice in accordance with the
above procedures and no inspection works were carried out, then the
CONTRACTOR can organize the inspection and the Engineer is obliged
to accept the CONTRACTOR's written records.
工程师不能按时进行验收,应在验收前24小时以书面形式向承包方提出延期要求,延期不能超过48小时。工程师未能按以上时间提出延期要求,不进行验收,承包方可自行组织验收,工程师应承认验收记录。
16.3 The engineering work is accepted to be qualified by the
Engineer and the work is in conformity with the required standard /
code and design requirement. The acceptance record shall be duly
signed by the Engineer, if the acceptance record is not signed by
the Engineer within 24 hours, it shall be deemed that the Engineer
agreed the record, so the CONTRACTOR can resume their concealed
work
经工程师验收,工程质量符合标准、规范和设计图纸等要求,验收24小时后,工程师不在验收记录上签字,视为工程师已经认可验收记录,承包方可进行隐蔽或继续施工。
17 Re-inspection
重新检验
Whether the engineering work is accepted by the Engineer or
not, the Engineer can request the re-inspection for the concealed
work, the CONTRACTOR shall tear open or drill the concealed work
for re-inspection as required and renew the work. If the
re-inspection proves qualified, the OWNER shall bear the additional
cost incurred and the work progress duly postponed; if the
re-inspection proves the work unqualified, the CONTRACTOR shall
bear all the expense therefrom and the work progress shall not be
postponed.
无论工程师是否进行验收,当其要求对已经隐蔽的工程重新检验时,承包方应按要求进行剥离或开孔,并在检验后重新覆盖或修复。检验合格,业主承担由此发生的全部追加合同价款,赔偿承包方损失,并相应顺延工期。检验不合格,承包方承担发生的全部费用,工期不予顺延。
18. Engineering test run
工程试车
18.1 The content of the test run over the engineering as
agreed by the both parties shall be in conformity with the
contractual scope of work for the installation by the
CONTRACTOR
双方约定需要试车的,试车内容应与承包方承包的安装范围相一致。
18.2 If
the installation work is ready for single machine load-free test
run, the CONTRACTOR shall organize such test run and inform the
Engineer in written form 48 hours prior to the test run. This
notice shall consist of the test run content, date / time and place
for the test run. The CONTRACTOR is required to prepare test run
record and the OWNER shall provide necessary conditions and
facilities for the test run work. If the test run proves qualified,
the Engineer shall sign his name on the test run
record.
设备安装工程具备单机无负荷试车条件,承包方组织试车,并在试车前48小时以书面形式通知工程师。通知包括试车内容、时间、地点。承包方准备试车记录,业主根据承包方要求为试车提供必要条件。试车合格,工程师在试车记录上签字。
18.3 If the Engineer fails to attend the test run in time, he
shall inform the CONTRACTOR in written form 24 hours prior to the
test run, but such postponement shall not be longer than 48 hours.
If the Engineer fails to inform the CONTRACTOR within the
designated period for postponement of test run and does not attend
the test run, it shall be deemed that the Engineer agreed the test
run record.
工程师不能按时参加试车,须在开始试车前24小时以书面形式向承包方提出延期要求,不参加试车,应承认试车记录。
18.4 When the installation work is ready for a load-free
integrated test run, the OWNER shall organize this work and inform
the CONTRACTOR in written form 48 hours prior to the test run. The
notice shall consist of the content and the date / time and place
of the test run. The CONTRACTOR shall make well-considered
preparatory work. If the test run proves qualified, the test run
record shall be signed by the both parties.
设备安装工程具备无负荷联动试车条件,业主组织试车,并在试车内容、时间、地点和对承包方的要求,承包方按要求做好准备工作。试车合格,双方在试车记录上签字。
18.5 Responsibilities of the both
parties双方责任
18.5.1 If the
test run does not conform to the acceptance requirement because of
the fault of the original design, the OWNER shall request the
design institute to modify the design and the CONTRACTOR shall
re-install the equipment as per the revised design. The OWNER shall
bear all expense for modification of design, tearing down of the
work and re-installation and add extra cost for the contract sum,
the work progress shall be duly postponed.
由于设计原因试车达不到验收要求,业主应要求设计单位修改设计,承包方按修改后的设计重新安装。业主承担修改设计、拆除及重新安装的全部费用和追加合同价款,工期相应顺延。
18.5.2 If the
test run does not reach the requirement for the acceptance due to
equipment manufacturing fault, the equipment supplier shall be
responsible for the purchase of the new equipment or repair work
while the CONTRACTOR is responsible for tear down and
re-installation work. If such equipment is purchased by the
CONTRACTOR, the CONTRACTOR shall be responsible for all the cost
for the new purchase of the equipment, tear down work and
re-installation, but the work progress shall not be postponed. If
the equipment is purchased by the OWNER, the OWNER shall bear all
the above mentioned cost, add extra cost for the contract value and
postpone the work progress duly.
由于设备制造原因试车达不到验收要求,由该设备采购一方负责重新购置或修理,承包方负责拆除和重新安装。设备由承包方采购的,由承包方承担修理或重新购置、拆除及重新安装的费用,工期不予顺延;设备由业主采购的,业主承担上述各项追加合同价款,工期相应顺延。
18.5.3 If the
test run is not in conformity with the acceptance requirement due
to the CONTRACTOR's fault, the CONTRACTOR shall re-install the work
and make the test run again and bear all the cost incurred, the
work progress shall not be postponed.
由于承包方施工原因试车不到验收要求,承包方按工程师要求重新安装和试车,并承担重新安装和试车的费用,工期不予顺延。
18.5.4 The OWNER
shall be responsible for all the expense incurred with the
exception of those already included in the contract sum and
stipulated in the Particular Conditions of Contract.
试车费用除已包括在合同价款之内或专用条款另有约定外,均由业主承担。
18.5.5 If the
qualified test runs acceptance record is not signed by the Engineer
within 24 hours after the test run, it can be deemed to be approved
by the Engineer, so the CONTRACTOR can resume their work or proceed
to complete the acceptance procedures.
工程师在试车合格后不在试车记录上签字,试车结束24小时后,视为工程师已经认可试车记录,承包方可继续施工或办理竣工手续。
18.6 Load test run shall be carried out by the OWNER after
the engineering work has been formally accepted. If the OWNER
wishes to carry out the test run prior to the acceptance and needs
cooperation from the CONTRACTOR, the OWNER shall have the approval
from the CONTRACTOR and the supplement agreement to be signed by
both parties.
投料试车应在工程竣工验收后由业主负责,如业主要求在工程竣工验收前进行或需要承包方配合时,应征得承包方同意,另行签订补充协议。
V Safety of Work
五、安全施工
19. Safety measures and safety
inspection 安全施工与检查
19.l The CONTRACTOR shall adhere the
relevant regulations on safety work in the construction work and
strictly carry out the work as per safety codes and is always ready
to accept the safety inspection and supervision, apply safety
measures to prevent any potential safety accident. The CONTRACTOR
shall be responsible for the cost resulting from the neglect of the
safety work by the CONTRACTOR.
承包方应遵守工程建设安全生产有关管理规定,严格按安全标准组织施工,并随时接受行业安全检查人员依法实施的监督检查,采取必要的安全防护措施,消除事故隐患。由于承包方安全措施不力造成事故的责任和因此发生的费用,由承包方承担。
19.2 Proceed safety orientation among the workers and staff
in the construction site and shall be responsible for their
personal safety. The OWNER shall not require the CONTRACTOR to
precede the construction work under violation of safety
regulations. The OWNER shall bear all the responsibilities and the
expense incurred due to their fault.
业主应对其在施工场地的工作人员进行安全教育,并对他们的安全负责。业主不得要求承包方违反安全管理的规定进行施工。因业主原因导致的安全事故,由业主承担相应责任及发生的费用。
20 Safety
Protection安全防护
20.1 The CONTRACTOR is required to provide safety facilities
and measures prior to the construction work or at the equipment
such as power equipment, power transmission line, underground
piping, sealed and vibration-proof workshop, work area exposed to
combustibles and explosives or adjacent to the traffic street., the
CONTRACTOR shall submit a safety measure report to the Engineer and
they can only start the work after the approval by the Engineer.
The CONTRACTOR shall bear all the expense on the safety facilities
work at work site.
承包方在动力设备、输电线路、地下管道、密封防震车间、易燃易爆地段以及临街交通要道附近施工时,施工开始前应向工程师提出安全防护措施,经工程师认可后实施,防护措施费用由承包方承担。
20.2 When carrying out the work in the fields of explosion,
and under the environment of radioactive and poisonous material
(including storage, transport and application) or application of
poisonous and corrosive material, the CONTRACTOR shall submit a
written notice to the Engineer 14 days prior to the construction
work attached with proposed measures and methods to be taken in the
work, the CONTRACTOR can proceed the work after the approval by the
Engineer. The CONTRACTOR shall bear all the expense for the safety
prevention measures and facilities.
实施爆破作业,在放射、毒害性环境中施工(含储存、运输、使用)及使用毒害性、腐蚀性物品施工时,承包方应在施工前14天以书面通知工程师,并提出相应的安全防护措施,经工程师认可后实施,由承包方承担安全防护措施费用。
21 Safety
Accident 事故处理
21.1 The CONTRACTOR shall report the department concerned
immediately and at the same inform the Engineer for any major
safety accident of death and injury and settle the accident as per
the requirement by the local authorities. The cost incurred to be
born by the party concerned.
发生重大伤亡及其他安全事故,承包方应按有关规定立即上报有关部门并通知工程师,同时按政府有关部门要求处理,由事故责任方承担发生的费用。
21.2 When there is dispute on who will be responsible for the
accident between the two parties, it shall be decided by the
decision from the department concerned.
业主承包方对事故责任有争议时,应按政府有关部门的认定处理。