2020版美国建筑工程施工合同》,这里再提供一份美国科罗拉多州《2021版美国建筑工程施工合同》。这份合同有一个特点,强化了The
Owner's Representative
(OR)代表业主对工程施工方施加的监督权力,相当于FIDIC合同中的工程师的权利。 部分章节示例如下: The aforementioned documents form
the Contract and what is required by any one shall be as binding as
if required by all. The intention of the Contract Documents is to
include all labor, materials, equipment and other items as provided
in Paragraph 10.2 necessary for the proper execution and completion
of the Work and the terms and conditions of payment therefore, and
also to include all Work which may be reasonably inferable from the
Contract Documents as being necessary to produce the intended
results. 上述文件构成了合同,任何一个文件的要求都应与所有文件的要求一样具有约束力。合同文件的意图是包括第10.2款规定的所有劳动、材料、设备和其他项目,这些都是正确实施和完成工程所必需的,以及因此而支付的条款和条件,还包括所有可以从合同文件中合理推断出的产生预期结果所必需的工作。 6.3 Two copies of the Contract Documents shall be signed by
the Owner and the Contractor. If either the Owner or the Contractor
do not sign the Drawings, Specifications, or any of the other
Contract Documents, the OR shall identify them. By executing the
Contract, the Contractor represents that he has visited the site
and familiarized himself with the local conditions under which the
Work is to be performed. 6.3